3-16-01 update
Para-Sealing The Outside Walls
A product called para-seal was placed on approximately the first six feet of the
outside of the retaining walls on the north side and west side of the Community Center
building. This product consists of a high-density polyethylene exterior with an expandable bentonite
clay layer. The product is tacked to the concrete with the bentonite layer against the building.
When the area is backfilled and the bentonite becomes wet it expands forming a seal which keeps
water from the base of the retaining walls. This is just one more thing that has been done to
protect the building from ground water.


These are very important elements of the construction project. It’s much
like baking a cake. If
you haven’t done a very good job of putting together the ingredients of your
cake, all of the
icing in the world won’t make it better. It’s the same with the foundation,
slab, and walls of a
building. The backfill material you see being placed in the figures above have
to meet a certain
compaction specification. As each lift of material is placed (no more than
6”-8” thick), it is
rolled repeatedly with what’s called a sheep’s foot roller (so-called due to
the protrusions
around the diameter of the steel roller). As the ground is rolled, the weight of
the machine in
combination with a vibrating action compacts the material to the desired spec. A
geo-tech comes
on site regularly to test the material to insure that it’s meeting the
compaction spec. These are
some of the ways we can gain a measure of confidence that we will not see
failures in critical
areas.
Gymnasium Floor
The first half of the gym floor was poured this week. The pour consisted of a 6
thick slab
utilizing a fiber mesh concrete. The contractor could have poured a
steel-reinforced 5 slab or
a 6 fiber mesh slab. XT opted for the 6 fiber mesh. This should be more than
adequate for the
sub-floor of the gym area. These specifications are set by Martin & Martin a
structural
engineering firm out of Denver, CO Mike Barrett, the structural engineer working
on the project,
is originally from Dove Creek, CO. We have been very pleased with the structural
engineering of
the entire project.


The project has been moving along very well in the last couple of weeks even
with the wet
weather. Next week we will begin to see the big glu-lam beams being erected. A
110-ton crane will
be on site by Monday the 19th to facilitate the erection of the beams. That will
be the subject
of the next report.