Community
center and lower site project
Update
12/29/2000
The Community Center and Lower Site Portion of the Phase I Project are
well underway. The last month has been spent doing mostly site work. The French
drain system I updated you on earlier is in place and working extremely well.
I’m not sure that the Council received this report. I sent it through the
Executive Office on 11/29/2000. If you didn’t receive a copy of this report,
please let me know and I will make another one for you. This reports details the
installation of the French drain system around the Community Center complete
with photos.
Once the French drain was installed, the area quickly dried up, allowing
Austin to proceed with the next phase of work. Installation of the mud slab and
the footers for the north side of the Community Center was completed. The mud
slab is a fairly wide slab pour that is used to create a nice flat surface on
top of the shale for the buildings footers. Since the mud slab and footer on the
north side have to support a fairly substantial retaining wall, they are poured
both wide and thick. The photos below illustrate what they look like.


After the mudslab and footer were poured, XL Concrete began forming for the retaining walls. The rebar for the columns is put in place and then the rest of the forms are constructed. This retaining wall will stabilize the area on the north side between Peaceful Spirit and the Community Center. This is required because we have a considerable amount of fill on the north side of the Community Center building. The resulting pressure from all of the fill material would be more than a normal wall structure could handle.


Other work that is currently underway at the Community Center is the underslab plumbing and the aeration system for under the gym floor. The aeration system consists of a series of PVC standpipes that are connected to perforated drainpipe that runs the length of the gym floor. While the system will pick up any water that happens to penetrate under the gym floor slab, the primary purpose is to provide aeration to eliminate any possible moisture build-up that could potentially cause problems for the wood gym floor. The underslab plumbing is primarily for drains, toilets, boiler room drains, etc.
Lower
Site Work
Firehawk
has completed a considerable amount of the initial lower site work such as
flattening, placing fill material, and working on the new alignment for Ute
Road. A portion of the new Ute Road work that has been particularly interesting
is the installation of an RCP (Rolled Concrete Pipe) that will be used to handle
the water from an old BIA irrigation ditch on the Lower Site. While I’m told
that the ditch hasn’t been used for irrigation purposes in quite sometime, it
does flow a fairly good amount of water. Most of the water in the ditch comes
from ground water drainage off the plateau to the west I suspect. I’m not sure
how much is actually coming from the Pine River. Construction of the RCP and
concrete headwalls has been anything but average. The area presented quite a few
problems for the construction crew as illustrated in the photos below.






Now
that the headwall and RCP have been placed, backfill will be installed over the
system and built up to where the new Ute Road can be completed to intersect with
County Road #517. The grade coming off the top of the hill and down to the lower
site will be at 8%. To put this in perspective, an 8% grade means that the road
will drop 8 feet in elevation vertically for every 100 feet it travels
horizontally. 8% is the maximum grade allowable under both State and Federal
regulations. To flatten this grade anymore than the 8% we would have had to use
a considerable additional amount of fill material which would have driven the
costs up considerably. There will be a flat spot on the top of the hill where it
meets the County Road that will allow four cars to be lined up while waiting for
traffic to clear before it slopes off to the 8% hill. Guardrail will be
installed along both sides of the road coming down off the hill to prevent cars
from sliding off into the wetlands.


The
lower site will undergo a tremendous face change over the next several months.
The photos above provide a hint to how much that will be. When the project is
complete the transformation should be something to behold. I believe it will be
something that the Tribe will like very much.
The
next month we will see a lot more concrete work being done at the Community
Center. I know that there are several people who are very skeptical of pouring
concrete in the winter months. There is always that fear that the cold weather
will compromise the concrete. As long as the proper precautions are being taken
as far as providing heat blankets to allow the concrete to cure properly there
should be no problem. In addition, Basin Engineering, the geotechnical company
who has been performing all of the soils tests, also monitors the concrete
pours. Cylinders are filled with the concrete being poured. Then at specific
intervals, the concrete in the cylinders is broken to verify its p.s.i. strength
(pounds per square inch). These breaks are usually done at 7, 14, and 21 days.
We receive the results of these breaks and they become a part of our permanent
construction file.